How Many Data Runs Does an ERP Implementation Really Need?

Ask five suppliers how many data runs your programme needs and you will hear five answers, usually the one that keeps their price lowest. It matters more than almost any line in the proposal, because data is where go-live dates are really decided.

In a survey of more than 100 SAP customers and experts by data migration specialist Xmateria, reported by SAPinsider in July 2026, 57% said data migration regularly delays their SAP projects. When it does, the typical slip is 10 to 25% of the planned timeline, and nearly a third of the delayed projects overran by up to 50%. Bloor Research puts it more bluntly: more than 60% of data migration projects overrun on time, budget or both.

57%say data migration regularly delays their SAP projectsXmateria via SAPinsider, 2026
10–25%typical slip to the timeline when it doesXmateria via SAPinsider, 2026
>60%of data migration projects overrun on time and/or budgetBloor Research
$12.9Maverage yearly cost of poor data quality to an organisationGartner, 2020

Across 30+ years of SAP and ERP deals, the story behind those numbers has been remarkably consistent. Data is rarely late because the tools are poor. It is late because too few full rehearsals were planned, the ones that were planned had no exit criteria, and nobody priced the time between runs to fix what each one found.

What a data run is, and what it isn't

A data run, also called a mock load, test load or trial conversion, is a complete pass through the migration: extract from the legacy systems, cleanse and transform, load into the new system, then reconcile back to the source. Loading a few hundred records for a demo is not a run. A run ends with a reconciliation the business signs, or it hasn't finished.

The short answer: three plus one

For a typical greenfield implementation with a single go-live, we plan for three mock loads and a full dress rehearsal, after an early profiling run. With fewer than that, the moment the business first reconciles real volumes on production-like data tends to arrive during cutover weekend. SAP's own guidance, published by SAP PRESS, recommends at least two productive load tests, data cleansing completed by the last of them, and the whole migration and cutover tested at least once before go-live.

Each run has a different job. Click through the ladder to see what each one should prove, and the exit targets we typically agree with clients.

Interactive · The run ladder

Six steps from legacy data to go-live

Select a run to see its purpose, volume and exit criteria.

Typical first-time load success target85%
Purpose
Volume & environment
Exit criteria
Who signs it off
What goes wrong if you skip it

Why every run needs a gap after it

A run is only as useful as the fix window that follows it. Each pass exposes mapping errors, missing values, duplicate records and transformation rules nobody wrote down. If the next run starts before those are fixed and re-tested, it simply finds the same defects again. In our experience, a full cycle of load, reconcile, fix and re-test takes three to five weeks on a mid-sized programme, and that time has to sit in the plan, not in somebody's weekend.

The shape you are looking for is simple: load success climbing towards 100% while open data defects fall towards zero. When the curves don't move between two runs, the problem is usually cleansing ownership, not technology.

Illustrative · A healthy data track

Quality should improve with every run

Load success rate and open data defects across a typical programme. Hover or tap a run for values.

Load success and open defects by data run Illustrative: load success rises from 85% at Mock 1 to 100% at cutover, while open defects fall from about 420 to near zero. 80%87%93%100% 0150300450
Load success, first time (left axis)Open data defects (right axis)

What changes the number

Three plus one is a starting point, not a rule. More legacy sources, poorer data, regulated processes, a tight cutover window or several go-live waves each add risk that only another rehearsal retires. A brownfield system conversion works differently again: the "runs" are technical conversions of a copy of production, and two full mock conversions before the dress rehearsal is the usual minimum. Try your own programme below.

Interactive · Data run planner

How many runs does your programme need?

Answer seven questions. The plan updates as you go.

4full runs before go-live: 3 mock loads and 1 dress rehearsal

    The cheapest line to cut from a bid

    When suppliers compete on price, data runs are one of the easiest things to trim. Each run is a few weeks of a small team, so dropping one takes a visible amount off the total. Putting the time back once go-live slips is never small, because by then the whole programme team, client and supplier, is waiting on the data.

    Interactive · The cost of a missing run

    One more run, or a later go-live?

    Enter rough figures for your programme. Slip scenarios use the range reported in the Xmateria research.

    Two bids, same headline price

    This is where data runs become a supplier selection issue rather than a delivery detail. Two proposals can arrive within a few percent of each other and describe very different programmes. The difference is rarely in the executive summary. It is in the migration approach, the RACI and the assumptions.

    How to read a proposal

    What the price includes is the real comparison

    Bid A

    €3.85M · looks 4% cheaper
    • ×Two mock loads, volume not stated
    • ×"Client responsible for data cleansing"
    • ×No exit criteria per run
    • ×Repeat runs treated as change requests
    • ×Dress rehearsal "if time permits"
    Risk sits with you, unpriced.

    Bid B

    €4.0M · shows its working
    • ✓Profiling run, three mocks, full dress rehearsal
    • ✓Shared cleansing plan with named owners
    • ✓Load and reconciliation targets per run
    • ✓One repeat run priced in as contingency
    • ✓Rehearsal timed against your cutover window
    Risk is visible, owned and priced.

    Ten questions to ask every supplier

    Put these to every bidder in clarifications, and score the answers. Vague answers are an answer too.

    Checklist · Supplier clarifications

    Can your preferred supplier answer all ten?

    0 of 10 answered

    Tick each question your preferred supplier has answered clearly in writing.

    A note for system integrators

    If you are on the bidding side, make the runs visible. Name each one, give it exit criteria, show the fix windows and price a contingency run. Evaluators comparing two similar prices will trust the proposal that shows how data actually gets to go-live, and it protects your margin as much as the client's timeline.

    Download the playbook

    Our free Data Runs Playbook puts all of this on paper: the run ladder with purpose, volume and exit criteria for each step, the sizing rules behind the planner, a cost-of-delay worksheet, a data RACI for client and supplier, a run-readiness checklist and the ten supplier questions as a scoring sheet. Every statistic is sourced.

    Free whitepaper · PDF

    The Data Runs Playbook: Planning Mock Loads That Protect Your Go-Live

    10 pages. No sign-up, no email required.

    Download the playbook

    Choosing an ERP supplier? Our buy-side tender support builds the data track into your requirement, so every bidder prices the same runs and you compare like with like. Book a free discovery call or email sales@dealcraftadvisory.ie.

    Sources

    1. SAPinsider, reporting Xmateria's research "The True Cost of Data Procrastination", July 2026. More than 100 SAP customers and experts surveyed over six months.
    2. Bloor Research, Data Migration.
    3. Gartner, Data Quality, citing Gartner research from 2020.
    4. SAP PRESS, What are the data migration phases for an SAP S/4HANA project?
    5. SAP Community, Planning the data migration track of an SAP project.

    Run targets, cycle durations, the planner's sizing rules and the illustrative chart reflect our practitioner experience, not a published standard. Agree your own criteria in the contract.